This topic describes how to stop a data synchronization project.

Limitations

The data transmission service allows you to stop a data synchronization project in the Paused, Failed, or Completed state.

Procedure

After a project is stopped, the project configurations are still retained. You can clear the project configurations and then reconfigure the project as needed. For more information, see Clear project configurations.

  1. Log on to the ApsaraDB for OceanBase console.

  2. In the left-side navigation pane, choose Data Transmission > Data Synchronization.

  3. On the Synchronization Projects page, click the More icon in the Actions column of the target project, and then click End in the drop-down list.

    image.png

    You can also click the project name to go to the project details page, click the More icon in the upper-right corner, and then click End in the drop-down list.

    image.png

  4. In the dialog box that appears, click OK.

What to do next

If a stopped subscription data synchronization project is no longer required, you can submit a ticket to apply for unsubscription in the Alibaba Cloud console. After the application is approved, the system will complete the refund and release and delete the project.