Service Upgrade

[Upgrade] Basic hardware:9th January 00:00-06:00 Beijing time Network switch upgrade

Dec 30, 2024

IT Hardware

Affected Time

2025-01-09 01:00:00 - 2025-01-09 06:00:00 (UTC+08) 东京 可用区A
2025-01-09 01:40:00 - 2025-01-09 06:00:00 (UTC+08) 雅加达 可用区C
2025-01-09 00:00:00 - 2025-01-09 05:00:00 (UTC+08) 首尔 可用区A

Change content

The change will conduct network switch upgrades and restart maintenance on the following nodes. The operations involve isolating and restoring the switches to eliminate software risks.

Tokyo-Availability Zone A
jakarta-Availability Zone C
seoul-Availability Zone A

Change Impact

During the process of isolating and restoring the network switches, there will be two jitters, with each one controlled within 5 seconds. Please try your best to avoid performing operations during this period. If there are business operations, please avoid the change window. We apologize for any inconvenience caused.